6/2022 Only one month after launching the rent of the apartments in Fragment, demand has been extraordinary. Clients are predominantly interested in the smaller studios, all of which are as of now fully rented out. The larger apartments, especially those with atypical layouts and terraces, are attracting increasing attention. 27. 6. 2022 Read more
5/2022 In the middle of May, we will launch the rent of the apartments in Fragment. The units will be ready in Q1 2023. 10. 5. 2022 Read more
3/22 The monolithic structure was completed right before the start of spring. Thanks to the intensive work on floors 1 to 5, which have previously been winterized, plasterboard walls, HVAC wiring, plastering, and cast floors are now finished. Preparatory work is also under way on the building’s interior. 1. 3. 2022 Read more
1/22 Windows are being installed, which are making the first complete areas in the house visible and also allow entrance number 3 to be finished. Interior tempering and HVAC work can now begin. The removal of the massive supporting props is also underway. 7. 1. 2022 Read more
12/2021 The installation of the windows and facades continues, while the upper floors are being concreted under the supervision of Skanska. The building’s first show flat is beginning to take shape. 8. 12. 2021 Read more
11/2021 Sipral windows were installed at the beginning of November and the installer began waterproofing the roof. At the same time, work on the walls between the apartments, the units’ interior partitions, and the basement is ongoing. 1. 11. 2021 Read more
10/2021 The construction of the residential bridge connecting the two wings of the building at the point in which they turn away from each other has been ongoing for the past few weeks. This is a major challenge in terms of structural engineering, but will allow apartments with truly unique interiors to be created. 11. 10. 2021 Read more
8/2021 As work on the monolithic structure continues, the walls and ceilings on the third through fifth floors were poured and lined. Consultations are currently underway regarding the sculptures and the landscaping around the building. 1. 8. 2021 Read more
5/2021 The concrete pour of the walls and ceilings on the first underground floor and the first two above-ground floors is underway. The most intense work is on the monolithic structures and insulation against vibrations caused by trams. 1. 5. 2021 Read more