Driving range Rohanský ostrov 18. 5. 2022 Share article: Related news 8/2021 As work on the monolithic structure continues, the walls and ceilings on the third through fifth floors were poured and lined. Consultations are currently underway regarding the sculptures and the landscaping around the building. 1. 8. 2021 Read more 5/2021 The concrete pour of the walls and ceilings on the first underground floor and the first two above-ground floors is underway. The most intense work is on the monolithic structures and insulation against vibrations caused by trams. 1. 5. 2021 Read more 3/22 The monolithic structure was completed right before the start of spring. Thanks to the intensive work on floors 1 to 5, which have previously been winterized, plasterboard walls, HVAC wiring, plastering, and cast floors are now finished. Preparatory work is also under way on the building’s interior. 1. 3. 2022 Read more
8/2021 As work on the monolithic structure continues, the walls and ceilings on the third through fifth floors were poured and lined. Consultations are currently underway regarding the sculptures and the landscaping around the building. 1. 8. 2021 Read more
5/2021 The concrete pour of the walls and ceilings on the first underground floor and the first two above-ground floors is underway. The most intense work is on the monolithic structures and insulation against vibrations caused by trams. 1. 5. 2021 Read more
3/22 The monolithic structure was completed right before the start of spring. Thanks to the intensive work on floors 1 to 5, which have previously been winterized, plasterboard walls, HVAC wiring, plastering, and cast floors are now finished. Preparatory work is also under way on the building’s interior. 1. 3. 2022 Read more