Etapa 18. 5. 2022 Share article: Related news 5/2021 The concrete pour of the walls and ceilings on the first underground floor and the first two above-ground floors is underway. The most intense work is on the monolithic structures and insulation against vibrations caused by trams. 1. 5. 2021 Read more 1/22 Windows are being installed, which are making the first complete areas in the house visible and also allow entrance number 3 to be finished. Interior tempering and HVAC work can now begin. The removal of the massive supporting props is also underway. 7. 1. 2022 Read more 12/2021 The installation of the windows and facades continues, while the upper floors are being concreted under the supervision of Skanska. The building’s first show flat is beginning to take shape. 8. 12. 2021 Read more
5/2021 The concrete pour of the walls and ceilings on the first underground floor and the first two above-ground floors is underway. The most intense work is on the monolithic structures and insulation against vibrations caused by trams. 1. 5. 2021 Read more
1/22 Windows are being installed, which are making the first complete areas in the house visible and also allow entrance number 3 to be finished. Interior tempering and HVAC work can now begin. The removal of the massive supporting props is also underway. 7. 1. 2022 Read more
12/2021 The installation of the windows and facades continues, while the upper floors are being concreted under the supervision of Skanska. The building’s first show flat is beginning to take shape. 8. 12. 2021 Read more