Kaizlovy Sady 18. 5. 2022 Share article: Related news 3/22 The monolithic structure was completed right before the start of spring. Thanks to the intensive work on floors 1 to 5, which have previously been winterized, plasterboard walls, HVAC wiring, plastering, and cast floors are now finished. Preparatory work is also under way on the building’s interior. 1. 3. 2022 Read more 8/2021 As work on the monolithic structure continues, the walls and ceilings on the third through fifth floors were poured and lined. Consultations are currently underway regarding the sculptures and the landscaping around the building. 1. 8. 2021 Read more 7/2022 Intensive interior work continues: we are finishing the carpentry in the apartments, laying tiles, wooden floors, finalizing the installation of equipment. Inside the building, all the professions necessary for the successful completion of the construction are being completed. 15. 7. 2022 Read more
3/22 The monolithic structure was completed right before the start of spring. Thanks to the intensive work on floors 1 to 5, which have previously been winterized, plasterboard walls, HVAC wiring, plastering, and cast floors are now finished. Preparatory work is also under way on the building’s interior. 1. 3. 2022 Read more
8/2021 As work on the monolithic structure continues, the walls and ceilings on the third through fifth floors were poured and lined. Consultations are currently underway regarding the sculptures and the landscaping around the building. 1. 8. 2021 Read more
7/2022 Intensive interior work continues: we are finishing the carpentry in the apartments, laying tiles, wooden floors, finalizing the installation of equipment. Inside the building, all the professions necessary for the successful completion of the construction are being completed. 15. 7. 2022 Read more