Můj šálek kávy 18. 5. 2022 Share article: Related news 7/2022 Intensive interior work continues: we are finishing the carpentry in the apartments, laying tiles, wooden floors, finalizing the installation of equipment. Inside the building, all the professions necessary for the successful completion of the construction are being completed. 15. 7. 2022 Read more 5/2021 The concrete pour of the walls and ceilings on the first underground floor and the first two above-ground floors is underway. The most intense work is on the monolithic structures and insulation against vibrations caused by trams. 1. 5. 2021 Read more 8/2021 As work on the monolithic structure continues, the walls and ceilings on the third through fifth floors were poured and lined. Consultations are currently underway regarding the sculptures and the landscaping around the building. 1. 8. 2021 Read more
7/2022 Intensive interior work continues: we are finishing the carpentry in the apartments, laying tiles, wooden floors, finalizing the installation of equipment. Inside the building, all the professions necessary for the successful completion of the construction are being completed. 15. 7. 2022 Read more
5/2021 The concrete pour of the walls and ceilings on the first underground floor and the first two above-ground floors is underway. The most intense work is on the monolithic structures and insulation against vibrations caused by trams. 1. 5. 2021 Read more
8/2021 As work on the monolithic structure continues, the walls and ceilings on the third through fifth floors were poured and lined. Consultations are currently underway regarding the sculptures and the landscaping around the building. 1. 8. 2021 Read more