Casa de Andalucía 18. 5. 2022 Share article: Related news 1/22 Windows are being installed, which are making the first complete areas in the house visible and also allow entrance number 3 to be finished. Interior tempering and HVAC work can now begin. The removal of the massive supporting props is also underway. 7. 1. 2022 Read more 5/2021 The concrete pour of the walls and ceilings on the first underground floor and the first two above-ground floors is underway. The most intense work is on the monolithic structures and insulation against vibrations caused by trams. 1. 5. 2021 Read more 10/2020 Construction officially commenced on October 1st during the groundbreaking ceremony. 1. 10. 2020 Read more
1/22 Windows are being installed, which are making the first complete areas in the house visible and also allow entrance number 3 to be finished. Interior tempering and HVAC work can now begin. The removal of the massive supporting props is also underway. 7. 1. 2022 Read more
5/2021 The concrete pour of the walls and ceilings on the first underground floor and the first two above-ground floors is underway. The most intense work is on the monolithic structures and insulation against vibrations caused by trams. 1. 5. 2021 Read more
10/2020 Construction officially commenced on October 1st during the groundbreaking ceremony. 1. 10. 2020 Read more