SABAI Karlín 18. 5. 2022 Share article: Related news 11/2023 Fragment Named the Best Residential Project 15. 11. 2023 Read more 5/2021 The concrete pour of the walls and ceilings on the first underground floor and the first two above-ground floors is underway. The most intense work is on the monolithic structures and insulation against vibrations caused by trams. 1. 5. 2021 Read more 3/22 The monolithic structure was completed right before the start of spring. Thanks to the intensive work on floors 1 to 5, which have previously been winterized, plasterboard walls, HVAC wiring, plastering, and cast floors are now finished. Preparatory work is also under way on the building’s interior. 1. 3. 2022 Read more
5/2021 The concrete pour of the walls and ceilings on the first underground floor and the first two above-ground floors is underway. The most intense work is on the monolithic structures and insulation against vibrations caused by trams. 1. 5. 2021 Read more
3/22 The monolithic structure was completed right before the start of spring. Thanks to the intensive work on floors 1 to 5, which have previously been winterized, plasterboard walls, HVAC wiring, plastering, and cast floors are now finished. Preparatory work is also under way on the building’s interior. 1. 3. 2022 Read more